Joseph Tegbe Addresses Electricity Supply Decline in Abuja, Lagos, and Additional States

The federal government expressed concern regarding declining electricity supply in affected areas including Abuja, Lagos, Ogun, Kwara, and Oyo States, blaming gas constraints, ongoing maintenance, and reduced hydropower generation.

The Minister of Power stated that preliminary assessments indicate disruptions stem from maintenance and operational power ecosystem issues coupled with generation decline from gas supply constraints to thermal stations and reduced hydroelectric output from lower water reservoir inflows.

The minister’s office engaged the Transmission Company of Nigeria, Nigerian Independent System Operator, and Distribution Companies toward resolving operational constraints behind downtime, accelerating ongoing maintenance, and maintaining public communication.

The ministry reaffirmed commitment toward supply reliability and quality improvement, assuring that Nigerians deserve improved power and the administration works toward delivery. The Nigerian Independent System Operator corroborated this position, attributing generation decline to gas supply constraints affecting thermal generating station capacity and reduced hydroelectric output from lower water inflows.

The reduction in available generation affected electricity quantum allocated to Distribution Companies for consumer supply, resulting in reduced supply hours and increased load shedding across distribution networks.

Regarding port equipment, the ministry facilitated clearance of 44 containers from Apapa ports out of over 300 stranded electrical equipment containers, some held since 2014, following President Tinubu’s directive. After clearance, technical experts will inspect equipment, deploy serviceable items in ongoing power projects, and dispose of remaining items appropriately.

The Niger Delta Power Holding Company recovered 110 abandoned containers and 216 packages, saving more than ₦30 billion and unlocking approximately 470 megawatts to the national grid through recovered turbines.